High-level project plan and delivery process

A nine-phase, gated programme from invitation and alignment through to ongoing support.


Detailed process by phase

This plan translates the engagement roadmap into a gated programme. Each phase produces defined outputs and must satisfy a decision gate before material resources are committed to the next stage. Durations are indicative.

  1. Phase 1. Invite & Alignment

    2–4 weeks

    Core process

    Confirm the sponsor, mandate, policy objectives, stakeholders, programme governance, reporting lines and engagement protocol. Hold inception workshops and agree the shared outcomes.

    Principal outputs

    Approved charter; stakeholder map; governance structure; initial risk register; communications plan.

    Decision / assurance point

    Gate 1A: Sponsor confirms mandate, authority and resources to proceed.

  2. Phase 2. Discovery & Project Scoping

    6–10 weeks

    Core process

    Review existing law, institutions, assets and studies; conduct site visits and interviews; establish the baseline; identify data gaps; define work packages, interfaces and procurement strategy.

    Principal outputs

    Diagnostic report; asset and data baseline; prioritised scope; programme schedule; cost range; data room.

    Decision / assurance point

    Gate 1: Scope is agreed and sufficient evidence exists to develop the business case.

  3. Phase 3. Feasibility

    6–12 months

    Core process

    Undertake demand, technical, engineering, environmental, social, legal, institutional, economic and financial studies. Compare options, test climate resilience and complete value-for-money and affordability assessments.

    Principal outputs

    Feasibility study; preferred option; concept design; ESIA/RAP pathway; financial model; implementation and risk plan.

    Decision / assurance point

    Gate 2: Preferred solution is technically feasible, economically justified, environmentally acceptable and capable of becoming bankable.

  4. Phase 4. Fund Acquisition

    6–18 months, overlapping late feasibility

    Core process

    Refine the funding strategy and transaction structure; prepare lender and investor materials; obtain government approvals; engage DFIs, grant providers and private investors; run procurement and negotiate agreements.

    Principal outputs

    Financing plan; information memorandum; procurement documents; term sheets; concession or funding agreements; conditions-precedent tracker.

    Decision / assurance point

    Gate 3: Financial close, committed funding and authority to establish and deliver.

  5. Phase 5. Establishment of Operating Enterprise

    6–9 months, parallel with design

    Core process

    Create or strengthen the legal entity; define target operating model, organisation and delegations; recruit leadership and critical staff; implement policies, systems, controls, licensing and training.

    Principal outputs

    Operational entity; board and management structure; approved policies; staffing plan; competency framework; core digital and financial systems.

    Decision / assurance point

    Readiness review: Enterprise can govern contracts, receive assets, regulate or operate safely, and account for funds.

  6. Phase 6. Build of Infrastructure

    24–60 months, corridor dependent

    Core process

    Complete detailed design and permits; procure works and equipment; manage construction, quality, safety, environment, interfaces and change; test assets; compile as-built records; commission the system.

    Principal outputs

    Completed infrastructure; certified systems; as-built drawings; asset register; operating and maintenance manuals; commissioning dossier.

    Decision / assurance point

    Gate 4: Independent assurance confirms safety, quality, performance and commissioning acceptance.

  7. Phase 7. Operations

    6–12 month ramp-up, then ongoing

    Core process

    Launch services through a controlled ramp-up; activate train control, maintenance, customer, revenue and incident processes; monitor performance; enforce licences and access rules; stabilise operations.

    Principal outputs

    Operating certificate; approved timetable; service-level baseline; safety and maintenance plans; performance dashboard; lessons log.

    Decision / assurance point

    Operational acceptance: Service meets agreed safety, reliability, capacity and financial thresholds.

  8. Phase 8. Transfer of Solution to State

    3–6 months

    Core process

    Verify contractual completion; transfer assets, records, licences, warranties, systems and knowledge; confirm staff capability; resolve defects and outstanding obligations; execute handover and acceptance.

    Principal outputs

    Transfer register; acceptance certificates; transferred asset and data records; trained state team; close-out report; residual-risk plan.

    Decision / assurance point

    Gate 5: State accepts ownership and operational accountability against defined acceptance criteria.

  9. Phase 9. Ongoing Support

    5–10 years or as contracted

    Core process

    Provide lifecycle maintenance support, periodic condition assessments, renewals planning, regulatory reviews, refresher training, performance optimisation and continuous process improvement.

    Principal outputs

    Maintenance and renewal plans; annual assurance reports; updated training and procedures; improvement backlog; long-term asset strategy.

    Decision / assurance point

    Annual assurance: Confirm continued safety, compliance, service performance and asset sustainability.


Cross-cutting management process

Six disciplines run alongside every phase of the programme.

Programme governance

Maintain a sponsor-led steering committee, programme management office, delegated decision rights, integrated schedule, budget control and monthly reporting.

Stakeholder engagement

Map affected institutions and communities, maintain a consultation calendar, record commitments, operate a grievance mechanism and communicate decisions transparently.

Environmental and social safeguards

Screen impacts from the outset, complete required studies and permits, manage resettlement and livelihoods, and monitor compliance through construction and operations.

Local content and skills transfer

Set measurable employment, supplier-development and training targets; pair international specialists with Sierra Leonean counterparts; verify competency before handover.

Risk, quality and assurance

Maintain integrated risk, issue and change registers; use independent technical and safety reviews at gates; audit deliverables against approved acceptance criteria.

Benefits realisation

Track safety, freight and passenger capacity, journey time, reliability, local employment, trade enablement, revenue and institutional capability from baseline through steady-state operations.